In many countries, government and regulators lead initiatives aimed at increasing the amount of renewable generation connection, putting pressure on network operators due to the increasing number of connection requests for new power plants at HV and/or MV level. DSOs have to provide to all the customers/renewable generation developers, a suitable connection to the existing distribution network. The adoption of Active Distribution Network management may offer new chances for increasing the hosting capacity of distributed generation and improving the performance of distribution operation and control, but requires the development of new reliability and cost evaluation techniques even more important as renewable power penetration in distribution system continues to increase significantly in the near future. In the paper, a pseudo-sequential Monte Carlo method (PSMC) able to evaluate the reliability of active distribution networks is proposed. The algorithm permits evaluating the expected energy not produced (EENP), the energy that is expectedly locked at any plant location due to distribution network limits, and/or the economic losses for the producer that accepts to be connected to the distribution network being conscious that his plant will be curtailed for network operation security reasons.

Pseudo Sequential Monte Carlo to plan the integration of RES in Active Distribution Networks

PILO, FABRIZIO GIULIO LUCA;GHIANI, EMILIO;SOMA, GIAN GIUSEPPE;CELLI, GIANNI
2011-01-01

Abstract

In many countries, government and regulators lead initiatives aimed at increasing the amount of renewable generation connection, putting pressure on network operators due to the increasing number of connection requests for new power plants at HV and/or MV level. DSOs have to provide to all the customers/renewable generation developers, a suitable connection to the existing distribution network. The adoption of Active Distribution Network management may offer new chances for increasing the hosting capacity of distributed generation and improving the performance of distribution operation and control, but requires the development of new reliability and cost evaluation techniques even more important as renewable power penetration in distribution system continues to increase significantly in the near future. In the paper, a pseudo-sequential Monte Carlo method (PSMC) able to evaluate the reliability of active distribution networks is proposed. The algorithm permits evaluating the expected energy not produced (EENP), the energy that is expectedly locked at any plant location due to distribution network limits, and/or the economic losses for the producer that accepts to be connected to the distribution network being conscious that his plant will be curtailed for network operation security reasons.
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11584/103173
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo

Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 3
  • ???jsp.display-item.citation.isi??? ND
social impact